Saturday 1 February 2020

Which of the following categories of a cost of quality report is an example of a cost incurred to detect poor-quality goods or services?



Which of the following situations indicate that a manager should consider using activity-based costing (ABC)?
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
The cost system is outdated.
·       
Older systems continue to operate at consistent levels of accuracy.
·       
The existing cost systems do not distort costs.
·       
YOU WERE SURE AND INCORRECT
The costs of implementing activity-based costing (ABC) exceeds the expected benefits.
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

A manager should consider using activity-based costing (ABC) if the cost system is outdated. If the costs of implementing activity-based costing (ABC) exceed expected benefits, if older systems continue to function, and if existing systems do not distort costs, then the existing cost system is appropriate.



Setting up a machine to change from producing one product to another is an example of a ________.
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
batch-level cost
·       
YOU WERE SURE AND INCORRECT
facility-level cost
·       
product-level cost
·       
unit-level cost
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Setting up a machine to change from producing one product to another is an example of a batch-level cost.

Inspecting and packaging are examples of unit-level costs.

Lease payment for the sole use of manufacturing is an example of a product-level cost.

Facility upkeep is an example of a facility-level cost.


________ have separate cost allocation rates for each activity identified by the company.
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
Activity-based costing (ABC) systems
·       
YOU WERE SURE AND INCORRECT
Plantwide cost allocation systems
·       
Departmental cost allocation systems
·       
All cost allocation systems
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Activity-based (ABC) systems have separate cost allocation rates for each activity identified by the company. The main difference between an ABC system and a plantwide or departmental cost allocation system is that ABC systems have separate cost allocation rates for each activity identified by the company. Thus, all cost allocation systems do not have separate cost allocation rates for each activity the manager identifies at the company.


In the cost allocation process, an allocation base ________.
ANSWER
INCORRECT
·       
usage collection is discouraged since it is never related to the allocation base
·       
THE CORRECT ANSWER
should be the cost driver of the costs in the particular activity pool
·       
YOU WERE SURE AND INCORRECT
is never a concern since managers never track activity pools
·       
using bar coding and other technological advances is discouraged since data collection is inconsistent
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

In the cost allocation process, an allocation base should be the cost driver of the costs in the particular activity pool. Managers always track how much of the allocation base a job or product uses. Managers always collect usage information about each allocation base. Bar coding and other technological advances encourage lower data collection costs and enhance the data collection process.


Which of the following choices represent conformance costs?
ANSWER
INCORRECT
·       
Appraisal and internal failure costs
·       
Internal and external failure costs
·       
YOU WERE SURE AND INCORRECT
Prevention and external failure costs
·       
THE CORRECT ANSWER
Appraisal and prevention costs
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Appraisal and prevention costs represent conformance costs. Internal and external failure costs are non-conformance costs.


Which of the following categories of a cost of quality report is an example of a cost incurred to detect poor-quality goods or services?
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
Appraisal costs
·       
Internal failure costs
·       
YOU WERE SURE AND INCORRECT
Prevention costs
·       
External failure costs
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

An appraisal cost is an example of a cost incurred to detect poor-quality goods or services. Other categories that form the framework for costs of quality report that exclude appraisal costs but outline other quality report costs include prevention costs, internal failure costs, and external failure costs.


Activity-based costing (ABC) ________.
ANSWER
INCORRECT
·       
allocates direct costs only to the products based on the type of activity
·       
THE CORRECT ANSWER
focuses on activities performed to produce a product
·       
YOU WERE SURE AND INCORRECT
results in the most amount of cost distortion among products
·       
focuses on departments instead of activities to produce a product
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Activity-based costing (ABC) focuses on activities performed to produce a product. ABC results in the least amount of cost distortion among products because indirect costs are allocated to the products based on types of activities and the extent to which the activities are used.


Activity-based costing (ABC) ________.
ANSWER
INCORRECT
·       
focuses on departments instead of activities to produce a product
·       
results in the most amount of cost distortion among products
·       
YOU WERE SURE AND INCORRECT
allocates direct costs only to the products based on the type of activity
·       
THE CORRECT ANSWER
focuses on activities performed to produce a product
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Activity-based costing (ABC) focuses on activities performed to produce a product. ABC results in the least amount of cost distortion among products because indirect costs are allocated to the products based on types of activities and the extent to which the activities are used.


In the cost allocation process, an allocation base ________.
ANSWER
INCORRECT
·       
is never a concern since managers never track activity pools
·       
using bar coding and other technological advances is discouraged since data collection is inconsistent
·       
YOU WERE SURE AND INCORRECT
usage collection is discouraged since it is never related to the allocation base
·       
THE CORRECT ANSWER
should be the cost driver of the costs in the particular activity pool
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

In the cost allocation process, an allocation base should be the cost driver of the costs in the particular activity pool. Managers always track how much of the allocation base a job or product uses. Managers always collect usage information about each allocation base. Bar coding and other technological advances encourage lower data collection costs and enhance the data collection process.


Setting up a machine to change from producing one product to another is an example of a ________.
ANSWER
INCORRECT
·       
facility-level cost
·       
YOU WERE SURE AND INCORRECT
product-level cost
·       
THE CORRECT ANSWER
batch-level cost
·       
unit-level cost
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Setting up a machine to change from producing one product to another is an example of a batch-level cost.

Inspecting and packaging are examples of unit-level costs.

Lease payment for the sole use of manufacturing is an example of a product-level cost.

Facility upkeep is an example of a facility-level cost.


Which of the following situations indicate that a manager should consider using activity-based costing (ABC)?
ANSWER
INCORRECT
·       
The existing cost systems do not distort costs.
·       
YOU WERE SURE AND INCORRECT
The costs of implementing activity-based costing (ABC) exceeds the expected benefits.
·       
Older systems continue to operate at consistent levels of accuracy.
·       
THE CORRECT ANSWER
The cost system is outdated.
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

A manager should consider using activity-based costing (ABC) if the cost system is outdated. If the costs of implementing activity-based costing (ABC) exceed expected benefits, if older systems continue to function, and if existing systems do not distort costs, then the existing cost system is appropriate.


Which of the following categories of a cost of quality report is an example of a cost incurred to detect poor-quality goods or services?
ANSWER
INCORRECT
·       
External failure costs
·       
Internal failure costs
·       
YOU WERE SURE AND INCORRECT
Prevention costs
·       
THE CORRECT ANSWER
Appraisal costs
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

An appraisal cost is an example of a cost incurred to detect poor-quality goods or services. Other categories that form the framework for costs of quality report that exclude appraisal costs but outline other quality report costs include prevention costs, internal failure costs, and external failure costs.


Which of the following statements best describes the relationship among activity-based costing and cost distortion among products?
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
Activity-based costing typically causes the least cost distortion between products because of the way indirect costs are allocated to the product.
·       
YOU WERE SURE AND INCORRECT
Activity-based costing distorts product costs, which ALWAYS result from the allocation of all indirect costs.
·       
Cost distortion is never a result of the way a manager allocates indirect costs.
·       
Activity based-costing causes the most cost distortion among product costs because indirect costs are allocated to products based on the extent to which the activities are used.
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Activity-based costing typically causes the least cost distortion between products because of the way indirect costs are allocated to the product. Activity-based costing causes the least distortion because managers allocate indirect costs to products based on the types and usage of product activities. Cost distortion results solely from the way a manager allocates indirect costs (manufacturing overhead).


The Laramie factory runs two departments: the Preparation Department and the Processing Department. The departmental overhead cost pool for the Preparation Department was $25,000 and was $20,000 for the Processing Department. The total amount of departmental allocation base was 400 DL hours in the Preparation Department and 600 DL hours in the Processing Department.
What is the estimated departmental overhead cost pool for each department?
ANSWER
INCORRECT
·       
$2.50 for the Processing Department and $2.00 for the Preparation Department
·       
YOU WERE SURE AND INCORRECT
$6.25 for the Processing Department and $3.33 for the Preparation Department
·       
$625.00 for the Processing Department and $333.33 for the Preparation Department
·       
THE CORRECT ANSWER
$62.50 for the Preparation Department and $33.33 for the Processing Department
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

The estimated departmental overhead cost pool for each department is $62.50 for the Preparation Department and $33.33 for the Processing Department. The calculations include:
Step 1: Total Departmental Overhead Cost Pool:
Preparation Department …………………..…….....…….$25,000
Processing Department …………………………..….......$20,000
Total Manufacturing Overhead (MOH) …………..…$45,000

Step 2: Total Amount of Departmental Allocation Base:
Preparation Department………………………………400 DL hours
Processing Department ………………………..……..600 DL hours

Step 3: Departmental Overhead Rates:
Preparation Department overhead rate = $25,000 / 400 = $62.50 per DL hour
Processing Department overhead rate =  $20,000 / 600 = $33.33 per DL hour

Which of the following choices represent conformance costs?
ANSWER
INCORRECT
·       
Appraisal and internal failure costs
·       
YOU WERE SURE AND INCORRECT
Prevention and external failure costs
·       
Internal and external failure costs
·       
THE CORRECT ANSWER
Appraisal and prevention costs
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Appraisal and prevention costs represent conformance costs. Internal and external failure costs are non-conformance costs.


Dobles Corporation has provided the following data from its activity-based costing system:

Activity Cost Pools
Estimated Overhead Cost
Expected Activity
Assembly
$228,060
18,000
machine-hours
Processing orders
$34,068
1,200
orders
Inspection          
$125,560
1,720
inspection-hours

The company makes 420 units of product D28K a year, requiring a total of 460 machine-hours, 80 orders, and 10 inspection-hours per year. The product's direct materials cost is $48.96 per unit, and its direct labor cost is $25.36 per unit.
Use activity-based costing to compute the unit product cost of product D28K.
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
$95.34 per unit
·       
$93.60 per unit
·       
YOU WERE SURE AND INCORRECT
$89.93 per unit
·       
$74.32 per unit
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

$95.34 per unit. The activity rates for each activity cost pool are computed as follows:
Activity Cost Pools
(a)
Estimated
 Overhead
 Cost
(b)
Total
 Expected
 Activity

(a) / (b)
Activity
 Rate
Assembly
$228,060
18,000
machine-hours
$12.67
per machine-hour
Processing orders
$34,068
1,200
orders
$28.39
per order
Inspection
$125,560
1,720
inspection-hours
$73.00
per inspection-hour

The overhead cost charged to Product D28K is:
Activity Cost Pools

Activity Rates

Expected Activity

Amount
 
Assembly
$12.67
per machine-hour
460
machine-hours
$5,828.20 
Processing orders
$28.39
per order
80
Orders
  2,271.20
Inspection          
$73.00
per inspection-hour
10
inspection-hours
    730.00 
Total overhead costs assigned  




$8,829.40

Direct materials (420 units × $48.96 per unit)
$20,563.20
Direct labor (420 units × $25.36 per unit)
  10,651.20
Overhead
  8,829.40
Total cost
$40,043.80

Unit product cost = $40,043.80 / 420 units = 
$95.34 per unit.



The first step in the development of an activity-based costing system is to ________.
ANSWER
INCORRECT
·       
compute activity cost allocation rates
·       
allocates manufacturing overhead
·       
YOU WERE SURE AND INCORRECT
select the allocation base and estimate total amounts
·       
THE CORRECT ANSWER
identify activity cost pools
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

The first step in the development of an activity-based costing system is to identify activity cost pools. Next, the manager selects the allocation base and estimates the total amounts, computes activity cost allocation rates, and allocates manufacturing overhead.


________ is a management philosophy and strategy focused on creating value for the customer by eliminating waste.
ANSWER
INCORRECT
·       
Eight wastes
·       
THE CORRECT ANSWER
Lean thinking
·       
Just-in-time (JIT)
·       
YOU WERE SURE AND INCORRECT
Kaizen

·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Lean thinking management philosophy and strategy focuses on creating value for the customer and eliminating waste.

Kaizen is a Japanese word meaning “change for the better.”

Eight wastes identifies the different waste found in traditional organizations, including service and merchandising companies. The eight wastes include (a) defects (b) overproduction (c) waiting (d) not utilizing people to their full potential (e) transportation (f) inventory (g) movement, and (h) excess processing.

Just-in-time (JIT) inventory philosophy focuses on purchasing raw materials just-in-time for production and then completing the finished goods just in time for delivery to customers.


Which of the following categories of a cost of quality report is an example of a cost incurred to detect poor-quality goods or services?
ANSWER
INCORRECT
·       
YOU WERE SURE AND INCORRECT
Prevention costs
·       
THE CORRECT ANSWER
Appraisal costs
·       
Internal failure costs
·       
External failure costs
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

An appraisal cost is an example of a cost incurred to detect poor-quality goods or services. Other categories that form the framework for costs of quality report that exclude appraisal costs but outline other quality report costs include prevention costs, internal failure costs, and external failure costs.


The Laramie factory runs two departments: the Preparation Department and the Processing Department. The departmental overhead cost pool for the Preparation Department was $25,000 and was $20,000 for the Processing Department. The total amount of departmental allocation base was 400 DL hours in the Preparation Department and 600 DL hours in the Processing Department.
What is the estimated departmental overhead cost pool for each department?
ANSWER
INCORRECT
·       
THE CORRECT ANSWER
$62.50 for the Preparation Department and $33.33 for the Processing Department
·       
$6.25 for the Processing Department and $3.33 for the Preparation Department
·       
$2.50 for the Processing Department and $2.00 for the Preparation Department
·       
YOU WERE SURE AND INCORRECT
$625.00 for the Processing Department and $333.33 for the Preparation Department
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

The estimated departmental overhead cost pool for each department is $62.50 for the Preparation Department and $33.33 for the Processing Department. The calculations include:
Step 1: Total Departmental Overhead Cost Pool:
Preparation Department …………………..…….....…….$25,000
Processing Department …………………………..….......$20,000
Total Manufacturing Overhead (MOH) …………..…$45,000

Step 2: Total Amount of Departmental Allocation Base:
Preparation Department………………………………400 DL hours
Processing Department ………………………..……..600 DL hours

Step 3: Departmental Overhead Rates:
Preparation Department overhead rate = $25,000 / 400 = $62.50 per DL hour
Processing Department overhead rate =  $20,000 / 600 = $33.33 per DL hour


Which of the following statements best describes the relationship among activity-based costing and cost distortion among products?
ANSWER
INCORRECT
·       
Activity based-costing causes the most cost distortion among product costs because indirect costs are allocated to products based on the extent to which the activities are used.
·       
THE CORRECT ANSWER
Activity-based costing typically causes the least cost distortion between products because of the way indirect costs are allocated to the product.
·       
YOU WERE SURE AND INCORRECT
Activity-based costing distorts product costs, which ALWAYS result from the allocation of all indirect costs.
·       
Cost distortion is never a result of the way a manager allocates indirect costs.
·       
I DON'T KNOW YET
WHAT YOU NEED TO KNOW

Activity-based costing typically causes the least cost distortion between products because of the way indirect costs are allocated to the product. Activity-based costing causes the least distortion because managers allocate indirect costs to products based on the types and usage of product activities. Cost distortion results solely from the way a manager allocates indirect costs (manufacturing overhead).

No comments:

Post a Comment