Thursday, 20 February 2020

KLM Co. is attempting to predict its maintenance costs more accurately. Maintenance costs and machine hours for the first four months are as follows:


KLM Co. is attempting to predict its maintenance costs more accurately. Maintenance costs and machine hours for the first four months are as follows:
 
Answer 


KLM Co. is



Required No. 1

Month Machine Hours Maintenance
Mar. 1430 8810
Apr. 1130 7850
Difference 300 960



Variable Cost per unit                      3.20 (960/300)



Required No. 2




Total Cost in Mar. 8810
Less: Variable Cost (3.20 x 1430)                    4,576
Fixed Cost                    4,234






Required No. 3

Fixed Cost                    4,234
Variable Cost (3.20 x 1400)                    4,480
Total Cost                    8,714

No comments:

Post a Comment