Garage, Inc., has identified the following two mutually exclusive projects: |
Year | Cash Flow (A) | Cash Flow (B) | |||||
0 | –$ | 28,300 | –$ | 28,300 | |||
1 | 13,700 | 3,950 | |||||
2 | 11,600 | 9,450 | |||||
3 | 8,850 | 14,500 | |||||
4 | 4,750 | 16,100 | |||||
a-1 |
What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)
|
IRR | ||
Project A | % | |
Project B | % | |
a-2 |
Using the IRR decision rule, which project should the company accept?
|
Project A |
a-3 | Is this decision necessarily correct? |
No |
b-1 |
If the required return is 10 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
|
NPV | ||
Project A | $ | |
Project B | $ | |
b-2 | Which project will the company choose if it applies the NPV decision rule? |
Project B |
c. |
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
|
Discount rate | % |
a.
The IRR is the interest rate that makes the NPV of the project equal to zero. The equation for the IRR of Project A is:
|
0 = –$28,300 + $13,700 / (1 + IRR) + $11,600 / (1 + IRR)2 + $8,850 / (1 + IRR)3 + $4,750 / (1 + IRR)4
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
IRR = 16.88% |
The equation for the IRR of Project B is: |
0 = –$28,300 + $3,950 / (1 + IRR) + $9,450 / (1 + IRR)2 + $14,500 / (1 + IRR)3 + $16,100 / (1 + IRR)4
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
IRR = 16.45% |
Examining the IRRs of the projects, we see that the IRRA is greater than the IRRB, so IRR decision rule implies accepting Project A. This may not be a correct decision; however, because the IRR criterion has a ranking problem for mutually exclusive projects. To see if the IRR decision rule is correct or not, we need to evaluate the project NPVs.
|
b.
The NPV of Project A is:
|
NPVA = –$28,300 + $13,700 / 1.10 + $11,600 / 1.102 + $8,850 / 1.103 + $4,750 / 1.104 |
NPVA = $3,634.77
|
And the NPV of Project B is: |
NPVB = –$28,300 + $3,950 / 1.10 + $9,450 / 1.102 + $14,500 / 1.103 + $16,100 / 1.104 |
NPVB = $4,991.41 |
The NPVB is greater than the NPVA, so we should accept Project B. |
c.
To find the crossover rate, we subtract the cash flows from one project from the cash flows of the other project. Here, we will subtract the cash flows for Project B from the cash flows of Project A. Once we find these differential cash flows, we find the IRR. The equation for the crossover rate is:
|
Crossover rate: 0 = $9,750 / (1 + R) + $2,150 / (1 + R)2 – $5,650 / (1 + R)3 – $11,350 / (1 + R)4 |
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
|
R = 15.46% |
At discount rates above 15.46 percent choose Project A; for discount rates below 15.46 percent choose Project B; indifferent between A and B at a discount rate of 15.46 percent.
|
Calculator Solution: |
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. |
Project A | |||
CFo
| –$28,300 |
CFo
| –$28,300 |
C01
| $13,700 |
C01
| $13,700 |
F01
| 1 |
F01
| 1 |
C02
| $11,600 |
C02
| $11,600 |
F02
| 1 |
F02
| 1 |
C03
| $8,850 |
C03
| $8,850 |
F03
| 1 |
F03
| 1 |
C04
| $4,750 |
C04
| $4,750 |
F04
| 1 |
F04
| 1 |
IRR CPT | I = 10% | ||
16.88% | NPV CPT | ||
$3,634.77 |
Project B | |||
CFo
| –$28,300 |
CFo
| –$28,300 |
C01
| $3,950 |
C01
| $3,950 |
F01
| 1 |
F01
| 1 |
C02
| $9,450 |
C02
| $9,450 |
F02
| 1 |
F02
| 1 |
C03
| $14,500 |
C03
| $14,500 |
F03
| 1 |
F03
| 1 |
C04
| $16,100 |
C04
| $16,100 |
F04
| 1 |
F04
| 1 |
IRR CPT | I = 10% | ||
16.45% | NPV CPT | ||
$4,991.41 |
Crossover rate | |
CFo | $0 |
C01 | $9,750 |
F01 | 1 |
C02 | $2,150 |
F02 | 1 |
C03 | –$5,650 |
F03 | 1 |
CO4 | –$11,350 |
FO4 | 1 |
IRR CPT | |
15.46% |
No comments:
Post a Comment