Problem 9-12 NPV versus IRR [LO1, 5]
| Garage, Inc., has identified the following two mutually exclusive projects: |
| Year | Cash Flow (A) | Cash Flow (B) | |||||
| 0 | –$ | 28,500 | –$ | 28,500 | |||
| 1 | 13,900 | 4,050 | |||||
| 2 | 11,800 | 9,550 | |||||
| 3 | 8,950 | 14,700 | |||||
| 4 | 4,850 | 16,300 | |||||
| a-1 |
What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)
|
| IRR | ||
| Project A | % | |
| Project B | % | |
| a-2 |
Using the IRR decision rule, which project should the company accept?
|
| Project A |
| a-3 | Is this decision necessarily correct? |
| No |
| b-1 |
If the required return is 11 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
|
| NPV | ||
| Project A | $ | |
| Project B | $ | |
| b-2 | Which project will the company choose if it applies the NPV decision rule? |
| Project B |
| c. |
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
|
| Discount rate | % |
a.
The IRR is the interest rate that makes the NPV of the project equal to zero. The equation for the IRR of Project A is:
|
0 = –$28,500 + $13,900 / (1 + IRR) + $11,800 / (1 + IRR)2 + $8,950 / (1 + IRR)3 + $4,850 / (1 + IRR)4
|
| Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
| IRR = 17.37% |
| The equation for the IRR of Project B is: |
0 = –$28,500 + $4,050 / (1 + IRR) + $9,550 / (1 + IRR)2 + $14,700 / (1 + IRR)3 + $16,300 / (1 + IRR)4
|
| Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
| IRR = 16.73% |
Examining the IRRs of the projects, we see that the IRRA is greater than the IRRB, so IRR decision rule implies accepting Project A. This may not be a correct decision; however, because the IRR criterion has a ranking problem for mutually exclusive projects. To see if the IRR decision rule is correct or not, we need to evaluate the project NPVs.
|
b.
The NPV of Project A is:
|
| NPVA = –$28,500 + $13,900 / 1.11 + $11,800 / 1.112 + $8,950 / 1.113 + $4,850 / 1.114 |
NPVA = $3,338.68
|
| And the NPV of Project B is: |
| NPVB = –$28,500 + $4,050 / 1.11 + $9,550 / 1.112 + $14,700 / 1.113 + $16,300 / 1.114 |
| NPVB = $4,385.47 |
| The NPVB is greater than the NPVA, so we should accept Project B. |
c.
To find the crossover rate, we subtract the cash flows from one project from the cash flows of the other project. Here, we will subtract the cash flows for Project B from the cash flows of Project A. Once we find these differential cash flows, we find the IRR. The equation for the crossover rate is:
|
| Crossover rate: 0 = $9,850 / (1 + R) + $2,250 / (1 + R)2 – $5,750 / (1 + R)3 – $11,450 / (1 + R)4 |
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
|
| R = 15.28% |
At discount rates above 15.28 percent choose Project A; for discount rates below 15.28 percent choose Project B; indifferent between A and B at a discount rate of 15.28 percent.
|
| Calculator Solution: |
| Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. |
| Project A | |||
CFo
| –$28,500 |
CFo
| –$28,500 |
C01
| $13,900 |
C01
| $13,900 |
F01
| 1 |
F01
| 1 |
C02
| $11,800 |
C02
| $11,800 |
F02
| 1 |
F02
| 1 |
C03
| $8,950 |
C03
| $8,950 |
F03
| 1 |
F03
| 1 |
C04
| $4,850 |
C04
| $4,850 |
F04
| 1 |
F04
| 1 |
| IRR CPT | I = 11% | ||
| 17.37% | NPV CPT | ||
| $3,338.68 | |||
| Project B | |||
CFo
| –$28,500 |
CFo
| –$28,500 |
C01
| $4,050 |
C01
| $4,050 |
F01
| 1 |
F01
| 1 |
C02
| $9,550 |
C02
| $9,550 |
F02
| 1 |
F02
| 1 |
C03
| $14,700 |
C03
| $14,700 |
F03
| 1 |
F03
| 1 |
C04
| $16,300 |
C04
| $16,300 |
F04
| 1 |
F04
| 1 |
| IRR CPT | I = 11% | ||
| 16.73% | NPV CPT | ||
| $4,385.47 | |||
| Crossover rate | |
| CFo | $0 |
| C01 | $9,850 |
| F01 | 1 |
| C02 | $2,250 |
| F02 | 1 |
| C03 | –$5,750 |
| F03 | 1 |
| CO4 | –$11,450 |
| FO4 | 1 |
| IRR CPT | |
| 15.28% | |
No comments:
Post a Comment