The manager of a crew that installs carpeting has tracked the crew’s output over the past several weeks, obtaining these figures: Week Crew Size Yards Installed 1 4 98 2 3 71 3 4 99 4 2 54 5 3 60 6 2 54 ________________________________________ a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.) Week Crew size Labour productivity (Yards) 1 4 24.50 2 3 23.67 3 4 24.75 4 2 27.00 5 3 20.00 6 2 27.00 ________________________________________ b. On the basis of your calculations, what can you conclude about crew size and productivity? Possibly even sized crews are better than odd sizes and a crew of 2 seems to work best.

The manager of a crew that installs carpeting has tracked the crew’s output over the past several weeks, obtaining these figures:
   
Week
Crew Size
Yards Installed
1
4
98
2
3
71
3
4
99
4
2
54
5
3
60
6
2
54

    
a.
Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.)
    
Week
Crew size
    Labour productivity
   (Yards)
1
4
24.50 correct    
2
3
23.67 correct    
3
4
24.75 correct    
4
2
27.00 correct    
5
3
20.00 correct    
6
2
27.00 correct    


   
b.
On the basis of your calculations, what can you conclude about crew size and productivity?
    


Possibly even correct  sized crews are better than odd correct  sizes and a crew of  2 correct  seems to work best.