Thursday, 19 July 2018

The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments—Fabrication and Assembly. Data for the products and departments are listed below.

  • Question 1

    1 out of 1 points


    Correct
    Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
     
    Activity
    Cost

    Activity Base
    Procurement
    $  370,000 
    Number of purchase orders
    Scheduling
      250,000
    Number of production orders
    Materials handling
      500,000
    Number of moves
    Product development
      730,000
    Number of engineering changes
    Production
    1,500,000
    Machine hours
     
     
    Number of
    Purchase
    Orders
     Number
    of
    Production
    Orders
    Number
    of
    Moves
    Number of Engineering
    Changes
    Machine
    Hours
    Number
    of
    Units
    Disk drives
    4,000
    300
    1,400
    10
     2,000
    2,000
    Tape drives
    4,000
    150
      800
     10
     8,000
    4,000
    Wire drives
    12,000 
    800
    4,000
    25
    10,000
    2,500

    Determine the activity rate per production order for scheduling.
    Selected Answer:
    a. 
    $200.00
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Activity Rate = Budgeted Activity Cost ÷ Total Activity-Base Usage​
    Activity
    Budgeted Activity Cost
    ÷
    Total Activity-Base Usage
    =
    Activity Rate
    Scheduling
    $250,000
    ÷
    1,250* orders
    ​=
    $200
    Activity-Base Usage
    Products
    Number of Production Orders
    Disk drives
    300 orders
    Tape drives
                       150
    Wire drives
                       800
    Total
                    1,250*orders
  • Question 2

    1 out of 1 points


    Correct
    Pinacle Corp. budgeted $700,000 of overhead cost for the current year. Actual overhead costs for the year were $650,000. Pinacle's plantwide allocation base, machine hours, was budgeted at 100,000 hours. Actual machine hours were 80,000. A total of 100,000 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is:
    Selected Answer:
    d. 
    $7.00 per machine hour
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Single Plantwide Factory Overhead Rate = Total Budgeted Factory Overhead ÷ Total Budgeted Plantwide Allocation Base
    Single Plantwide Factory Overhead Rate = $700,000 ÷ 100,000 machine hours = $7 per machine hour
  • Question 3

    1 out of 1 points


    Correct
    The Skagit Company manufactures Hooks and Nooks. The following shows the activities per product and total activity information:
     
    Setups
    Inspections
    Assembly (dlh)
    Hooks - 4,000 units
    1
    3
    1
    Nooks - 8,000 units
    2
    2
    3
        
          Activity Pool
    Activity Base
    Budgeted Amount
    Setups
    20,000
    $  60,000
    Inspections
    24,000
    120,000
    Assembly (dlh)
    28,000
    420,000

    Calculate the total factory overhead to be charged to Nooks.
    Selected Answer:
    b. 
    $488,000
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    The total factory overhead to be charged to Nooks = $61* × 8,000 units = $488,000
    Activity
    Budgeted Activity Cost
    ÷
    Activity-Base Usage
    =
    Activity Rate
    ×
    Activity Usage
    =
    Activity Cost
    Setups
    $60,000
    ÷
    20,000 setups
    =
    $3 per setup
    ×
    2 setups
    =
    $ 6
    Inspections
    $120,000
    ÷
    24,000 inspections
    =
    $5 per inspection
    ×
    2 inspections
    =
      10 
    Assembly (dlh)
    $420,000
    ÷
    28,000 dlh
    =
    $15 per dlh
    ×
    3 dlh
    =
       45 
    Total
      $61*
  • Question 4

    1 out of 1 points


    Correct
    The Botosan Factory has determined that its budgeted factory overhead budget for the year is $13,500,000 and budgeted direct labor hours are 10,000,000. If the actual direct labor hours for the period are 350,000, how much overhead would be allocated to the period?
    Selected Answer:
    d. 
    $472,500
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Single Plantwide Factory Overhead Rate = Total Budgeted Factory Overhead ÷ Total Budgeted Plantwide Allocation Base
    Single plantwide factory overhead rate = $13,500,000 ÷ 10,000,000 budgeted direct labor hours = $1.35 per direct labor hour
    Overhead allocated to the period = Single plantwide factory overhead rate × Actual direct labor hours for the period = $1.35 × 350,000 direct labor hours = $472,500
    Overhead allocated to the period is $472,500.
  • Question 5

    1 out of 1 points


    Correct
    Everest Co. uses a plantwide factory overhead rate based on direct labor hours. Overhead costs would be overcharged to which of the following departments?
    Selected Answer:
    a. 
    A labor-intensive department
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 6

    1 out of 1 points


    Correct
    Adirondak Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead.
     
    Overhead
    Total
    Direct
    Labor Hours
    DLH per Product
     A 
     B 
    Painting Dept.
    $250,000
    10,000
    16
     4
    Finishing Dept.
      75,000
    12,000
     4
    16
       Totals
    $325,000
    22,000
    20
    20

    Calculate the plantwide factory overhead rate for Adirondack Marketing Inc.
    Selected Answer:
    c. 
    $14.77 per dlh
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Single Plantwide Factory Overhead Rate = Total Budgeted Factory Overhead ÷ Total Budgeted Plantwide Allocation Base
    Single Plantwide Factory Overhead Rate = $325,000 ÷ 22,000 direct labor hours = $14.77 per direct labor hour
  • Question 7

    1 out of 1 points


    Correct
    The Dawson Company manufactures small lamps and desk lamps. The following shows the activities per product and the total overhead information:
     
    Setups
    Inspections
    Assembly (dlh)
    Small Lamps - 3,000 units
    8,000
    9,000
    16,000
    Desk Lamps - 6,000 units
    16,000
    15,000
    12,000
        
    Activity PoolActivity BaseBudgeted Amount
    Setups
    24,000
    $60,000
    Inspections
    24,000
    $120,000
    Assembly (dlh)
    28,000
    $280,000

    Calculate the overhead per unit to be charged to small lamps.
    Selected Answer:
    a. 
    $75.00
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    The overhead per unit to be charged to the small lamps = $225,000* ÷ 3,000 small lamps = $75 per small lamp
    Activity
    Budgeted Activity Cost
    ÷
    Activity-Base Usage
    =
    Activity Rate
    ×
    Activity Usage
    =
    Activity Cost
    Setups
    $60,000
    ÷
    24,000 setups
    =
    $2.50 per setup
    ×
    8,000 setups
    =
    $  20,000
    Inspections
    $120,000
    ÷
    24,000 inspections
    =
    $5.00 per inspection
    ×
    9,000 inspections
    =
        45,000
    Assembly (dlh)
    $280,000
    ÷
    28,000 dlh
    =
    $10.00 per dlh
    ×
    16,000 dlh
    =
      160,000
    Total
     $225,000*
  • Question 8

    1 out of 1 points


    Correct
    Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours.
     
    Overhead
    Direct Labor
    Hours (dlh)
    Product
     A 
     B 
    Painting Dept.
    $248,000
    10,000 dlh
      16 dlh    4 dlh
    Finishing Dept.
      72,000
        10,000         
           4           16     
       Totals
    $320,000
    20,000 dlh
      20 dlh   20 dlh

    Determine the overhead from both production departments allocated to each unit of Product A if Blue Ridge Marketing Inc. uses a multiple department rate system.
    Selected Answer:
    a. 
    $425.60 per unit
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Allocation Base Usage per Unit
    ×
    Production Department Factory Overhead Rate
    =
    Allocated Factory Overhead per Unit of Product
    Product A
    Painting Department
    16 direct labor hours
    ×
    $24.80* per dlh
    =
    $396.80
    Finishing Department
    4 direct
    labor hours
    ×
    $ 7.20** per dlh
    =
        28.80
    Total overhead cost per unit of Product A
    $425.60
    Production Department Factory Overhead Rate = Budgeted Department Factory Overhead ÷ Budgeted Department Allocation Base
    Overhead rate per hour for the Painting Department = $248,000 ÷ 10,000 estimated direct labor hours = $24.80*
    Overhead rate per hour for the Finishing Department = $72,000 ÷ 10,000 estimated direct labor hours = $7.20**
  • Question 9

    1 out of 1 points


    Correct
    Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
     
    Activity
    Cost

    Activity Base
    Procurement
    $  370,000 
    Number of purchase orders
    Scheduling
      250,000
    Number of production orders
    Materials handling
      500,000
    Number of moves
    Product development
      730,000
    Number of engineering changes
    Production
    1,500,000
    Machine hours
     
     
    Number of
    Purchase
    Orders
     Number
    of
    Production
    Orders
    Number
    of
    Moves
    Number of Engineering
    Changes
    Machine
    Hours
    Number
    of
    Units
    Disk drives
    4,000
    300
    1,400
    10
     2,000
    2,000
    Tape drives
    4,000
    150
      800
     10
     8,000
    4,000
    Wire drives
    12,000 
    800
    4,000
    25
    10,000
    2,500

    Determine the activity-based cost for each disk drive unit.
    Selected Answer:
    b. 
    $279.57
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    The activity-based cost for each disk drive = $559,132* ÷ 2,000 units = $279.57​
    Activity
    Activity-Base Usage
    ×
    Activity Rate
    =
    Activity Cost
    Procurement
    4,000 orders
    ×
    $18.50 per order
    =
    $  74,000  
    Scheduling
    300 orders
    ×
    $200 per order
    =
      60,000
    Materials handling
    1,400 moves
    ×
    $80.65 per move
    =
     112,910
    Product development
    10 engineering changes
    ×
    $16,222 per change
    =
     162,222
    Production
    2,000 machine hours
    ×
    $75 per machine hour
    =
     150,000
    Total
      $559,132*
  • Question 10

    1 out of 1 points


    Correct
    Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
     
    Activity
    Cost

    Activity Base
    Procurement
    $  370,000 
    Number of purchase orders
    Scheduling
      250,000
    Number of production orders
    Materials handling
      500,000
    Number of moves
    Product development
      730,000
    Number of engineering changes
    Production
    1,500,000
    Machine hours
     
     
    Number of
    Purchase
    Orders
     Number
    of
    Production
    Orders
    Number
    of
    Moves
    Number of Engineering
    Changes
    Machine
    Hours
    Number
    of
    Units
    Disk drives
    4,000
    300
    1,400
    10
     2,000
    2,000
    Tape drives
    4,000
    150
      800
     10
     8,000
    4,000
    Wire drives
    12,000 
    800
    4,000
    25
    10,000
    2,500

    Determine the activity rate for product development per change.
    Selected Answer:
    d. 
    $16,222
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Activity Rate = Budgeted Activity Cost ÷ Total Activity-Base Usage​
    Activity
    Budgeted Activity Cost
    ÷
    Total Activity-Base Usage
    =
    Activity Rate
    Product development
    $730,000
    ÷
    45* changes
    =
    $16,222
    ​​
    Activity-Base Usage
    Products
    Number of Engineering Changes
    Disk drives
    10 changes
    Tape drives
                        10
    Wire drives
                        25
    Total
     45* changes
  • Question 11

    1 out of 1 points


    Correct
    Using multiple department factory overhead rates instead of a single plantwide factory overhead rate:
    Selected Answer:
    d. 
    results in more accurate product costs
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 12

    1 out of 1 points


    Correct
    Common allocation bases are
    Selected Answer:
    c. 
    direct labor dollars, direct labor hours, machine hours
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 13

    1 out of 1 points


    Correct
    The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments—Fabrication and Assembly. Data for the products and departments are listed below.
    Product
    Number of units
    Labor hrs
    per unit
    Machine hours
    per unit
    Rings
    1,000
    4
    6
    Dings
    2,000
    3
    9
    All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.

    The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.

    What is the Fabrication Department overhead rate per machine hour?
    Selected Answer:
    c. 
    $3.75
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Fabrication Department overhead rate per machine hour = $90,000 / 24,000 machine hours= $3.75​
    Product
    Number of Units
    ×
    Machine Hours per Unit
    =
    Total Labor Hours
    Rings
    1,000 units
    ×
    6 machine hours
    =
    6,000 machine hours
    Dings
    2,000 units
    ×
    9 machine hours
    =
    18,000 machine hours
    Total
    24,000 machine hours*
  • Question 14

    1 out of 1 points


    Correct
    Blackwelder Factory produces two similar products - small lamps and desk lamps. The total plant overhead budget is $640,000 with 400,000 estimated direct labor hours. It is further estimated that small lamp production will require 275,000 direct labor hours and desk lamp production will need 125,000 direct labor hours.

    Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to desk lamp production if actual direct hours for the period is 118,000?
    Selected Answer:
    a. 
    $188,800
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Single Plantwide Factory Overhead Rate = Total Budgeted Plant Overhead ÷ Total Budgeted Plantwide Allocation Base
    Single Plantwide Factory Overhead Rate= $640,000 ÷ 400,000 direct labor hours = $1.60 per direct labor hour
    Overhead allocated to the period = Single plantwide factory overhead rate × Actual direct labor hours for the period for desk lamp production = $1.60 × 118,000 direct labor hours = $188,800
    The factory overhead allocated to desk lamp production is $188,800.
  • Question 15

    1 out of 1 points


    Correct
    Activity rates are determined by
    Selected Answer:
    d. 
    dividing the cost budgeted for each activity pool by the estimated activity base for that pool.
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 16

    1 out of 1 points


    Correct
    Given the following information, determine the activity rate for setups.
    Activity Pool
    Activity Base
    Budgeted Amount
    Setups
    10,000
    $180,000
    Inspections
    24,000
    $120,000
    Assembly (DLH)
    80,000
    $400,000
    Selected Answer:
    b. 
    $18.00
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Activity Rate = Budgeted Activity Cost ÷ Total Activity-Base Usage
    Activity rate for setups = $180,000 ÷ 10,000 setups = $18.00 per setup
  • Question 17

    1 out of 1 points


    Correct
    The Beauty Beyond Words Salon uses an activity-based costing system in its beauty salon to determine the cost of services. The salon has determined the costs of services by activity as follows:
    ActivityActivity Rate
    Hair washing$4.00
    Conditioning$3.50
    Chemical treatment$25.00
    Styling$10.00
     
    Hair Washing

    Conditioning
    Chemical Treatment
    Styling
    Haircut1100
    Complete style1101
    Perm2311
    Highlights3421

    Calculate the cost of services for a haircut.
    Selected Answer:
    b. 
    $7.50
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    The cost of services for a haircut = $7.50*
    Activity
    Activity Rate
    ×
    Activity Usage
    =
    Activity Cost
    Hair washing
    $4 per hair wash
    ×
    1
    =
    $4.00 
    Conditioning
    $3.50 per conditioning
    ×
    1
    =
     3.50
    Chemical treatment
    $25 per treatment
    ×
    0
    =
     0.00
    Styling
    $10 per styling
    ×
    0
    =
     0.00
    Total
     $7.50*
  • Question 18

    1 out of 1 points


    Correct
    Using a plantwide factory overhead rate distorts product costs when:
    Selected Answer:
    c. 
    both A and B are true
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 19

    1 out of 1 points


    Correct
    Activity-based costing for selling and administrative expenses can also be beneficial in allocating expenses to various products. Which of the following is the best allocation base for help desk costs?
    Selected Answer:
    d. 
    Number of calls
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 20

    1 out of 1 points


    Correct
    Which of the following are the two most common allocation bases for factory overhead?
    Selected Answer:
    b. 
    Direct labor hours and machine hours
    Answers:
    a. 

    b. 

    c. 

    d. 
  • Question 21

    0 out of 1 points


    Incorrect
    The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments—Fabrication and Assembly. Data for the products and departments are listed below.
    Product
    Number of units
    Labor hrs
    per unit
    Machine hours
    per unit
    Rings
    1,000
    4
    6
    Dings
    2,000
    3
    9
    All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.

    The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.

    What is the Assembly Department overhead rate per labor hour?
    Selected Answer:
    a. 
    $3.75
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Assembly Department overhead rate per labor hour = $105,000 / 10,000 direct labor hours* = $10.50
    Product
    Number of Units
    ×
    Labor Hours per Unit
    =
    Total Labor Hours
    Rings
    1,000 units
    ×
    4 direct labor hours
    =
    4,000 direct labor hours
    Dings
    2,000 units
    ×
    3 direct labor hours
    =
    6,000 direct labor hours
    Total
    10,000 direct labor hours*
  • Question 22

    1 out of 1 points


    Correct
    The Kaumajet Factory produces two products - table lamps and desk lamps. It has two separate departments - Finishing and Production. The overhead budget for the Finishing Department is $550,000, using 500,000 direct labor hours. The overhead budget for the Production Department is $400,000 using 80,000 direct labor hours.

    If the budget estimates that a desk lamp will require 1 hours of finishing and 2 hours of production, how much factory overhead will the Kaumajet Factory allocate to each unit of desk lamps using the multiple production department factory overhead rate method with an allocation base of direct labor hours?
    Selected Answer:
    a. 
    $11.10
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Allocation Base Usage per Unit
    ×
    Production Department Factory Overhead Rate
    =
    Allocated Factory Overhead per Unit of Product
    Desk lamp
    Finishing Department
    1 direct labor hour
    ×
    $1.10* per dlh
    =
    $ 1.10
    Production Department
    2 direct labor hours
    ×
     $5.00** per dlh
    =
      10.00
    Total overhead cost per table lamp
    $11.10
    ​​Production Department Factory Overhead Rate = Budgeted Department Factory Overhead ÷ Budgeted Department Allocation Base
    Overhead rate per hour for the Finishing Department = $550,000 ÷ 500,000 estimated direct labor hours = $1.10* per direct labor hour
    Overhead rate per hour for the Production Department = $400,000 ÷ 80,000 estimated direct labor hours = $5.00** per direct labor hour
  • Question 23

    1 out of 1 points


    Correct
    The Kaumajet Factory produces two products - table lamps and desk lamps. It has two separate departments - Finishing and Production. The overhead budget for the Finishing Department is $550,000, using 500,000 direct labor hours. The overhead budget for the Production Department is $400,000 using 80,000 direct labor hours.

    If the budget estimates that a desk lamp will require 1 hours of finishing and 2 hours of production, what is the total amount of factory overhead the Kaumajet Factory will allocate to desk lamps using the multiple production department factory overhead rate method with an allocation base of direct labor hours, if 26,000 units are produced?
    Selected Answer:
    d. 
    $288,600
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Factory overhead allocated to 26,000 desk lamps = $11.101 × 26,000 units = $288,600​
    Production Department Factory Overhead Rate = Budgeted Department Factory Overhead ÷ Budgeted Department Allocation Base
    ​Overhead rate per hour for the Finishing Department = $550,000 ÷ 500,000 estimated direct labor hours = $1.10* per direct labor hour
    Overhead rate per hour for the Production Department = $400,000 ÷ 80,000 estimated direct labor hours = $5.00** per direct labor hour​
    Allocation Base Usage per Unit
    ×
    Production Department Factory Overhead Rate
    =
    Allocated Factory Overhead per Unit of Product
    Desk lamp
    Finishing Department
    1 direct labor hour
    ×
    $1.10* per dlh
    =
    $ 1.10 
    Production Department
    2 direct labor hours
    ×
     $5.00** per dlh
    =
    10.00
    Total overhead cost per table lamp
    $11.101
  • Question 24

    1 out of 1 points


    Correct
    Blackwelder Factory produces two similar products - small lamps and desk lamps. The total plant overhead budget is $640,000 with 400,000 estimated direct labor hours. It is further estimated that small lamp production will require 275,000 direct labor hours and desk lamp production will need 125,000 direct labor hours.

    Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to small lamp production if actual direct hours for the period is 285,000?
    Selected Answer:
    d. 
    $456,000
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Single Plantwide Factory Overhead Rate = Total Budgeted Plant Overhead ÷ Total Budgeted Plantwide Allocation Base
    Single Plantwide Factory Overhead Rate = $640,000 ÷ 400,000 direct labor hours = $1.60 per direct labor hour
    Overhead allocated to small lamp production = Single plantwide factory overhead rate × Actual direct labor hours for the period for small lamp production = $1.60 × 285,000 direct labor hours = $456,000
    The factory overhead allocated to small lamp production is $456,000.
  • Question 25

    1 out of 1 points


    Correct
    The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments—Fabrication and Assembly. Data for the products and departments are listed below.
    Product
    Number of units
    Labor hrs
    per unit
    Machine hours
    per unit
    Rings
    1,000
    4
    6
    Dings
    2,000
    3
    9
    All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.

    The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.

    What is the overhead cost per unit for Dings?
    Selected Answer:
    a. 
    $65.25
    Answers:
    a. 

    b. 

    c. 

    d. 
    Response Feedback:
    Rationale:
    Overhead cost per unit for Dings = (Assembly Department overhead rate per labor hour × Labor hours per unit) + (Fabrication Department overhead rate per machine hour × Machine hours per unit)
    Overhead cost per unit for Dings = ($10.501 × 3 direct labor hours) + ($3.752 × 9 machine hours) = $31.50 + $33.75 = $65.25​
    Assembly Department overhead rate per labor hour = $105,000 / 10,000 direct labor hours* = $10.501​​
    Product
    Number of Units
    ×
    Labor Hours per Unit
    =
    Total Labor Hours
    Rings
    1,000 units
    ×
    4 direct labor hours
    =
    4,000 direct labor hours
    Dings
    2,000 units
    ×
    3 direct labor hours
    =
    6,000 direct labor hours
    Total
    10,000 direct labor hours*
    Fabrication Department overhead rate per machine hour = $90,000 / 24,000 machine hours** = $3.752
    Product
    Number of Units
    ×
    Machine Hours per Unit
    =
    Total Labor Hours
    Rings
    1,000 units
    ×
    6 machine hours
    =
    6,000 machine hours
    Dings
    2,000 units
    ×
    9 machine hours
    =
    18,000 machine hours
    Total
    24,000 machine hours**

No comments:

Post a Comment